1.
What is the purpose and mission of a PMO? The mission statement defines achievable and
measurable objectives and identifies the responsibilities, and hence services,
of the PMO.
The general purpose of a PMO was to realize
the benefits that came from consistent project practices such as IT
improvements in project performance, efficiency, and resource utilization to
enterprise improvements in cost management and corporate capability to launch
products.
At AtekPC, the current responsibilities of a PMO were
limited to IT projects even though there were ongoing discussions about
expanding its scope to an enterprise level PMO that would include business
projects in the future. The specific duties of the PMO were typically divided
into two categories: project-focused and enterprise-oriented. Project-focused
responsibilities such as consulting, mentoring, and training were services that
enabled the success of individual projects. On the other hand, enterprise
responsibilities addressed services that might improve all projects such as
portfolio management, PM standards, methods, and tools, and project performance
archives. To that end, the PMO continued to build support from the functional
areas and IT personnel involved in these projects.
2.
What are the main challenges and obstacles in
implementing a PMO? The governance model
establishes the domain of control, its organizational level of accountability,
and its authority.
In 2007, information systems projects were typically
operational or maintenance efforts undertaken at the request of a particular functional
area. They were generally small to medium-sized projects in terms of both size
and duration, and they were managed informally without standardized practices. The Director of Application Development stated
“we had a lot of operational projects going on and a lot of enhancements going
on, but we had very few enterprise applications going on. As we began to take a
look at what we needed to do in the future, we realized that we had to really hone
our skills to be able to move more aggressively and sure-footedly through
projects and to be able to handle multiple projects at one time."
The changing environment that AtekPC faced created a
number of challenges which they were planning to address with projects on a
large and complex scale. The PMO was being introduced in order to provide
standardization in managing these projects and to gain improvements in the
planning and performance of the initiatives. Although AtekPC had undertaken a
few large projections in the past that had employed some formal practices, these
projects had not resulting in lasting formalization of practices.
One of the key challenges AtekPC faced is their
distribution of IT projects to staff. IT projects were
typically managed by adding PM responsibilities to one of the development staff
who were assigned to specific functional areas. Lead Analysts assumed the role
of project manager and supervised workgroups of analysts and programmers of
varying skill levels, and they were responsible for satisfying the requests of
the functional areas as well as the performance of their workgroups. The
manager resolved any issues and conflicts, the request processed, executed, and
delivered through the Lead Analyst. Project methods, documentation, practices,
and tools were individualized by the Lead Analyst with little or no consistency
across IT groups or business areas.
Although AtekPC thought this informal
approach was benefit to their organization, not having consistency and
standardization across IT groups and business areas could cause several
internal conflicts within the organization. IT was viewed as a peripheral job
function to the core business activities. As a result, IT had been seen as an
order-taker, expected to provide service on demand. During the past decade,
projects had become increasingly focused on operations and maintenance in an
over-riding effort to improve efficiencies within the business functions. The
development of cross-functional integration systems and the use of internet
technologies were only two of many emerging needs as AtekPC struggled with radical
changes in its industry and marketplace.
The new required projects were large
and complex and they involved multiple functional areas and multiple technological
areas unlike the narrow focused projects that were performed in the past. The
demands of these new initiatives and projects were expected to overtax the
current informal project management methods. However, implementing a PMO at AtekPC
was itself a challenge which required skillful management to be successful. A
difficult balance had to be maintained both between maintenance and new
development as well as between resources that went into development activities
versus resources that went into project management activities under the new
PMO.
Another area of concern was where the responsibilities
fell for the PMO. The specific duties of a PMO were typically divided into two
categories: project-focused and enterprise-oriented. Project-focused
responsibilities such as consulting, mentoring, and training were services that
enabled the success of individual projects. Clarification of these project responsibilities
of the PMO was continuously evolving at AtekPC. One of the major limitations of
the PMO was the shortage of expert resources available to support these
projects.
In the other category, enterprise responsibilities
addressed services that might improve all projects such as portfolio
management, PM standards, methods, and tools, and project performance archives.
Enterprise-oriented responsibilities for the new PMO were slow to develop at
AtekPC. The enterprise-focused services developed by Nelson’s PMO team were
being well received. While progress in this area was constrained by the limited
PMO resources, there was a clear agreement even at the CIO level that the PMO
was responsible for establishing, publishing, and disseminating project
practices, standards, and tools. On the other hand, portfolio management (the change
from managing one-off projects to the establishment of techniques for managing
continuous streams of projects) and archiving responsibilities (the
establishment of archival records of projects for knowledge sharing) were not
being addressed.
Another concern was the issue of authority. Strider
decided that enforcement of these new project practices required formal authority,
and he was prepared to provide that only when the PMO had proven itself to the
business and IT. Due to the culture of AtekPC, support had to start from the
top and not all of the senior staff was equally enthused about the PMO concept.
In this case, authority was primarily being developed bottom-up through the
value of the PMO services. Even this was limited to those functional areas and
IT areas actively engaging the PMO. There was no current plan to enforce usage
at the enterprise level.
3.
What structural and governance mechanisms are
critical to effective PMO implementation?
The structural model determines its degree of centralization, staff
allocations, and level of direct project management.
At the one extreme, PMO-heavy was characterized by a full
staff of project managers who assumed responsibility for the management of all
IT projects. This model focused on the acquisition of project management
experts, either from internal or external sources, and used these resources to
manage projects under the direction of the PMO. In the extreme version of
PMO-heavy, no project would operate outside the management and direct control
of the PMO. At the other end of the spectrum, PMO-light was characterized by a minimal
staff of experts who worked through internal project managers to perform the
responsibilities of the PMO. This model focused on the development of the
skills of internal project managers who were not formally connected with the PMO.
In the extreme version of PMO-light, all projects operated outside of the PMO
under existing organizational controls, and the ownership of projects resided
within the functional area and IT group charged with execution of the project.
While Nelson was agreeable to working with a small team
at the start, he felt that the delays from this approach might compromise their
ability to provide PMO services and to demonstrate its worth to the functional
areas of the business. However, he and the other managers recognized that resources
were not free, and they had to come from someplace which meant reducing the
capabilities of someone else’s work to advance his own. If he didn’t have
constraints, he would prefer a team that consisted of project analyst and
managers that could be new and as you go on, you could pull from the
organization. In this approach the team would be getting a various range of
experience and ability. Nelson felt there was not enough education about
project management to know the difference between PMO light and PMO heavy. With
these processes and procedures that we’re developing we’ll establish project
planning, tracking, initiation, and closure. All the project managers will help
get the IT house in order.
Gardner had the expectation that the PMO model would be
more heavy than light. In his understanding the PMO would provide a project
manager resource pool and use the “idea form” to capture new project requests.
Gardner viewed the organization model as one where “they were moving from just
helping us with methodology types of things to managing projects, they are
thinking of a pool of project managers”. Resources would be assigned in a matrix
structure for the duration of the project where you would have one key manager
working on your project.
On the other hand, Field recognized that the problem of a
PMO-heavy structure was not only about IT staffing in bringing on project
managers and analysts, it’s also the business resources. Today, we have line
managers who are working on multiple projects in addition to their regular
jobs, and they can’t take on any more. What really drives a lot of the projects
in any company is the availability of the business resources to work on those projects.
Having the business resources available is already becoming a problem for us.
With a PMO-light we are lined up better with the business side in terms of the
number of resources, and it’s a better balance.
With some functional areas in support, the PMO team
continued their implementation efforts. As Nelson remarked, their advancement
to date had been in “baby steps.” The frustration of such tedious progress
tempted them to consider an alternative approach –- force the change with
top-down mandates and hired experts. Several managers, including those directly
involved with the PMO, recognized the need for a larger staff of experts to
build standards and methods quickly, and they advocated a rapid, more resource
intensive implementation strategy. Such an approach would allow the PMO to
prove its value by actively managing more projects and helping AtekPC to
achieve more consistent and better project performance. IT management was
concerned that such an approach would fail because they couldn’t force radical
change on AtekPC. Thus, the senior IT managers encouraged a slow, incremental
strategy that would allow the PMO concept to prove it.
While not widely discussed, PMO governance has some
importance. At present, there were no roadmaps or timelines for its maturation
so there was no way to measure PMO performance other than through the subjective
opinions of those involved. There was a sense that AtekPC would know whether
the PMO was working if the projects were getting done and the company was getting
what it needed. One worry of the companies is whether project management would
slow down the company and they needed to prove the value. Given the approach of
measuring PMO performance through subjective consensus and anecdotal data, the
next governance issue was figuring out to whom was the PMO accountable.
Currently reports are given Director Steinberg, but in theory he should not get
the reports. Strider recognizes that the current governance model was only
temporary, but explains that in order to get the PMO established, he needed to
secure support from the planning office and the SVP to take to IT. AtekPC has
not determined which department the PMO will be part of or be more of a hybrid.
4. How
much PM is enough PM? How much PMO
support is enough PMO support? The
cultural impact of the PMO on the organization is assessed by the receptivity
to PM and the amount of organizational flux.
IT management realized that in the future they would
depend on standards and consistent processes to manage their projects and drive
them forward. Nonetheless, implementing a PMO in a non-PM environment was
challenging because it went against the grain of the organizational culture.
Many people within AtekPC viewed project management as just administrative
overhead—something that would inevitably get in the way of doing “real work.”
Field described the cultural challenge facing the new PMO:
“We
are moving from a company that had really no formal project management to a company
that would like to be very formal. We are going to be somewhere in the middle.
We can’t be so rigid about project management. This culture is not going to let
us do that. You have to mix the culture in with the methods and the processes,
and now I even hear where the processes can’t be that rigid. If we go too
rigid, it will fail. We have to be a little fluid and dynamic at times, and
that upsets some PMO folks, but we have to do it that way here. To succeed we
have to develop an organization that will be flexible and will be accurate in
its reporting. So that’s my struggle -– having project management fit into a
culture that is changing but is not quite over here yet.”
The forces opposing the PMO seemed overwhelming at times
to those involved. Strider wondered how willing the IT organization itself was
toward changing their processes and adapting to new project management
practices as this was a key cultural issue. Many of the staff had little or no
experience with formal project management practices. Very few knew how to use
any of the software tools available such as Microsoft Project. In addition to
these knowledge barriers, the informality of the current practices was seen as
highly attractive by many. The IT staff also found the informality appealing since
there was no cost tracking nor were any performance records kept on the
projects. The functional areas were not accountable for measuring the benefits
resulting from their projects, and the IT project staff was not working within an
assigned project budget. Another source of resistance was the lack of
understanding at all levels of the value of formal project management.
Altogether these sources of resistance to a PMO created formidable cultural
barriers to its success that management and the PMO team had to address.
The PMO implementation strategy at AtekPC was to work
within the culture and to develop forces that would promote the PMO and overcome
cultural resistance. Promotional forces included the mentoring, coaching, and
training that were being provided by the PMO team. The company was clearly
under pressure to change the way it did business, but there was no consensus among
senior management concerning the degree to which the PMO was integral to the
change process. The PMO had to become a part of the AtekPC culture and that
requires small changes over a long period of time. If the PMO found itself
fighting against the culture, it would definitely fit, so it was important to
have the support needed for the PMO to succeed.
In Strider’s opinion it was too soon to apply formal
authority without evidence of value and without more widespread support for the
PMO concept. He believed that more buy-in was needed from the functional areas
first. One of the chief cultural issues in his mind was how quickly the functional
areas are willing to adapt to a more formal process. They would have to be
willing to prioritize projects and make the tough choices and tradeoffs.
To compete in a changing industry in which consolidation
was occurring, AtekPC had implemented a corporate Planning Office. Recognizing
the role that IT would likely play in enabling AtekPC to respond to the
industry pressures, the senior vice-president had supported the creation of a PMO
within IT. The role of the PMO might be expanded to include non-IT projects if
it proved to be successful. At the same time, there was a possibility that the
PMO might fail due to the challenge of implementing such a measured and disciplined
approach to projects in an environment where that was viewed as foreign to the
culture.
Reflection
In class it was recommended to go with a PMO light for the
short term and shift to a PMO heavy in the long term. In alignment with the
recommendation, it’s also important to set milestones and hard deadlines for
the organization to adhere to so that time, utilization, and efficiencies are
being achieved. If you allow the company to slowly migrate with no end date,
there is no confirmation that the migration will ever be successfully
completed. There is also no way to accurately budget such a migration without
having timelines of steps in place.
Implementing a PMO structure would allow for improvements in
cost management and the capability to launch additional products and services.
One of the key benefits will be the standardization of many of the processes
that can showcase to their vendors that there is structure and reliance in the
AtekPC organization and that if you worked with one team, you would get the
same quality as another team.
Much of the conversation was around the culture of AtekPC. In
many companies especially in large organizations, a culture switch can be initiated
and carried out by the head of the company. There is something to valuing entrepreneurial
spirit and having less structure, however this is a technology company.
Although this could cause a shock to the company, a shock may be just what the
company needs instead of employees relying on what they know and being comfortable.
Where many job functions and processes would benefit from standardization and
proper methodology. If senior management team begin to act in accordance to a
culture shift than the rest of the organization should follow suit. AtekPC
could benefit by giving employees incentives (i.e. bonuses) for implementing
these changes by specific deadlines which can spur friendly competition or even
new and improved ways of working that could tie in the current culture mixed
with the new PMO structure in a hybrid capacity.
No comments:
Post a Comment